Addagrip approved contractor Total Protection (GB) Ltd was appointed to install 2127sqm of Addastone resin bonded gravel to match existing surfaced areas at the Lee Valley White Water Centre , a London 2012 Olympic venue which opened to the public in September 2012.
As the areas to be surfaced would be subjected to heavy vehicle use, Total Protection recommended using an aggregate with a higher PSV value to improve lifespan. The client selected 1-3mm Brittany Bronze aggregate.
Due to the nature of the contract, the deadlines for scheduling of work and ordering of materials were tight and the weather presented its usual challenges. Despite this, work was completed to schedule in November 2013.
Testimonial
The client was pleased with the result, advising that the work was carried out “in a sound and professional manner which we are pleased to say exceeded expectations in Quality, Health & Safety and Environmental Management terms.”